Beginning MS Project 2003
Creating a new Project
Project
- a series of task that have a defined start time and end time.
To open MS Project 2003:
-
Click on
Start
,
Programs
,
Microsoft Office
,
Microsoft Project 2003
.
-
In the task pane window, click on
Create a New Project
.
Entering Tasks
Task
- a specific action that needs to be completed in a project.
-
On the project guide toolbar, click on
Task
.
-
In the Gantt chart, under the task name column of the first cell, type in the name of a task.
-
Press
Enter
, to go to the next cell and continue entering tasks.
-
Delete a task by clicking on
Edit,
Delete Task
.
-
Insert a task by clicking on
Insert, New Task
.
Continue until you list all tasks that define your project.
Setting Durations
Duration
- the time it takes to complete a task.
Note:
by default, durations are displayed as days. To change the default, click on
Tools
, click on
Options
, click on the
Schedule tab
, under
Duration is entered in:
Click on the desired duration setting.
-
Click on the duration cell for the task row that you would like to set.
-
For Days, Click on the duration cell, and type in number of days (if not on default, type
D
).
-
For Hours, click in the duration cell, and type in the number of hours followed the letter
H
.
-
For Minutes, click on the duration cell, and type in the number of minutes followed by the letter
M
.
-
For Months, click in the duration cell, and type in the number of months followed by the letters
MO
.
-
For Weeks, click in the duration cell, and type in the number of weeks followed by the letter
W
.
Note:
To modify durations you can retype the new duration or click and drag the graphical representation.
Modifying The Calendar
-
Click on
Tools
, click on
Options
, click on the
Calendar tab
.
-
Under
Calendar Options
, click on the drop down menus and choose your appropriate settings.
-
To change days you are available to work on the project, click on
Tools
, click on
Change Working Time
.
-
Under
Select date(s)
, click on the day you are not available or
click on the letter of the week to choose that day every week.
-
Under
Set selected date(s) to
, change the radial button to
non-working time
, click
OK
.
Setting Milestones
Milestone
- something that needs to be achieved but does not have a duration.
-
Click on the tasks duration cell where you would like the set a milestone.
-
Type
0d
in the duration for that task.
A black diamond with a date will show in the project gantt chart graph window, indicating a milestone.
Develop a Summary Task
Summary Task
- a grouping of tasks that logically belong together.
-
Click on the first task, in the list of tasks, where you want a summary task.
-
Click
Insert
, click
New Task
, type the name of the summary task.
-
Highlight all of the of the tasks to be summarized by holding down the shift key and clicking on each of them.
-
Click
Indent
on the toolbar.
Linking Tasks
-
Highlight the two tasks to be linked by holding down the shift key and clicking on each of them.
-
Click on
Task
on the project toolbar.
-
Click on
Schedule tasks
in the task pane display.
-
Choose between the following setting:
Finish to Start
- (most common) used when you need a task to finish before another one starts.
Start to Start
- used when you want two tasks to start simultaneously.
End to End
- used when you want two tasks to end simultaneously.
Note:
To break a link, click on the
break link
icon in the task pane display.